ICC Hotel

Project data

Location: Darling Harbour, Sydney, Australia

  • 37 storey Hotel to service the recently completed International Convention Centre.
  • At level 26 a unique V Shape façade was introduced on the building. The façade effectively introduced a slab cantilever of 400mm, which increased in length at every new slab level, eventually being 21m long. 

Requirements

  • Providing 25m high LPS to the perimeter of building once topped out
  • Providing hydraulic climbing system

Customer

Dalma Form Specialists

Benefit to customer

PERI’s self-climbing LPS hydraulic system freed up crane time to enable a 4 day slab cycle

PERI solution

  • PERI LPS was used to provide the screen perimeter protection.
  • PERI Skydeck owned by the customer was used to form the concrete slabs.